End of assembly Puidoux

Things are moving forward: the assembly of our first Swiss system has been completed on schedule. Cold commissioning is now starting. A wood-fired combined heat and power plant has been built here, which provides 0.78 MW of electricity and supplies heat for the district heating network. The firing capacity of the plant is 4.2 MW and produces hot water at 95 °C for a district heating network and in the first construction stage [...]